NumberTitleWPLead beneficiaryDue Date (in months)Means of verificationStatus
MS1 Website ready WP1, WP7 1 - CREAF 1 Website up and runningO.K.
MS2 Internal kick-off WP1 1 - CREAF 1 Minutes of the meeting become availableo.k.
MS3 ENEON setup WP3 3 - TIWAH 2 ENEON list of participants publishedUnclear
MS4 Plenary workshop WP3 3 - TIWAH 2 Minutes of the meeting become availableDelayed
MS5 SDG workshop WP2 3 - TIWAH 4 Minutes of the meeting become availableDelayed
MS6 GA methodology defined WP6 1 - CREAF 4 Checklist for gap analysis availableUnclear
MS7 Inventory database designed; population and analysis methodologies defined WP4 4 - 52N 5 List of requirements and inventory design received and confirmed by CNRUnclear
MS8 Collocated EV workshop WP2 6 - CMCC 6 Minutes of the meeting become availableO.k.
MS9 Industrial challenges defined WP5 1 - CREAF 6 List and definition of each challenge published on the websiteUnclear
MS10 Pyranometric data is delivered for testing WP5 10 - ARMINES 7 Data received and verifiedUnclear
MS11 EV defined WP2 6 - CMCC 8 List of EV confirmed by CNRUnclear
MS12 Energy data model for industry challenge designed WP5 10 - ARMINES 8 Design is distributed to the PTBUnclear
MS13 Observation inventory population 1st loop completed WP4 2 - CNR 10 Queries to the inventory returns complete resultsunclear
MS14 Energy industry challenge platform open for testing WP5 10 - ARMINES 12 Instructions for testing become availableUnclear
MS15 Observation inventory analysis 1st loop produced WP4 2 - CNR 12 Challenge conclusions shared with the PTB and PABunclear
MS16 Collocated challenges workshop WP5 10 - ARMINES 13 Minutes of the meeting become available Associated with document Ref. Ares(2014)unclear
MS17 Collocated citizen science workshop WP3 5 - IIASA 13 Minutes of the meeting become availableunclear
MS18 End of energy challenge WP5 10 - ARMINES 14 Challenge conclusions shared with the PTB and PAB
MS19 End of RS & insitu challenge WP5 10 - ARMINES 15 Challenge conclusions shared with the PTB and PAB
MS20 Gaps analysis 1st loop completed WP6 3 - TIWAH 15 Gap analysis conclusions shared with the PTB and PAB
MS21 Priorities 1st loop completed WP6 3 - TIWAH 17 Priorities conclusions shared with the PTB and PAB
MS22 Observation feedback system published WP4 7 - S&T Corp. 18 User feedback up and running
MS23 Collocated GA workshop WP6 3 - TIWAH 18 Minutes of the meeting become available
MS24 End of in-situ DAB challenge WP5 10 - ARMINES 19 Some new in-situ services integrated in the DAB
MS25 Observation inventory population final loop completed WP4 2 - CNR 21 Queries to the inventory returns complete results
MS26 Gaps analysis final loop completed WP6 3 - TIWAH 22 Gap analysis conclusions shared with the PTB and PAB
MS27 Plenary workshop M22 WP7 3 - TIWAH 22 Minutes of the meeting become available
MS28 Observation inventory analysis final loop produced WP4 2 - CNR 23 Challenge conclusions shared with the PTB and PAB
MS29 End of exemplary application challenge WP5 10 - ARMINES 23 Conclusions of the application challenge shared with the PTB and PAB
MS30 Priorities final loop completed WP6 3 - TIWAH 24 Priorities conclusions shared with the PTB and PAB
MS31 Exploitation plan starts WP7 1 - CREAF 24 Exploitation Plan is delivered to the EC